Professional Scrum Master I: free practice exam

Free PSM I mock test

A free PSM I practice test: 20 realistic questions covering the official focus areas, with instant results and a detailed explanation for every question. About 15 minutes, no account needed.

Over 2,000 candidates have prepared with PrepForScrum.

No account, no signup: your answers are saved as you go.

Prefer a structured plan? Get the free 2-week study plan

PSM I sample questions, answered and explained

12 questions in the style of the real PSM I exam, solved and explained. The free test above uses 20 different ones. Every correct answer is marked, with an explanation based on the Scrum Guide 2020.

  1. Question 1 · Scrum Theory and Principles

    How does the Scrum Guide 2020 describe Scrum itself?

    • A lightweight framework that helps people and organizations generate value through adaptive solutions for complex problems
    • A complete methodology that prescribes the practices and documents needed for product development
    • A project management standard that defines phases, gates, and governance for delivery work
    • A collection of engineering and delivery practices for incrementally building, testing, and releasing software in short cycles

    Why: The Definition of Scrum describes it as a lightweight framework that helps people, teams, and organizations generate value through adaptive solutions for complex problems. Scrum is deliberately not a methodology, a standard, or a set of engineering practices; those can be employed within the framework but are not part of it.

  2. Question 2 · Scrum Team and Accountabilities

    What does a Scrum Team consist of?

    • One Scrum Master, one Product Owner, and Developers
    • One Scrum Master, one Product Owner, and a lead for each specialty
    • A Product Owner, Developers, and a project manager who reports progress
    • A Scrum Master, analysts, testers, and programmers as separate groups

    Why: The Scrum Team section defines the Scrum Team as one Scrum Master, one Product Owner, and Developers. There are no sub-teams, no hierarchies, and no additional accountabilities such as project manager or specialty lead.

  3. Question 3 · Scrum Framework

    What does the Scrum Guide 2020 say about the length of a Sprint?

    • Sprints are fixed length events of one month or less
    • Sprints last two weeks unless the Product Owner agrees otherwise
    • Sprint length is chosen per Sprint to match the selected work
    • Sprint length follows the release cycle agreed with stakeholders

    Why: The Sprint section states that Sprints are fixed length events of one month or less to create consistency. Shorter Sprints generate more learning cycles and limit risk to a smaller time frame, but the length is set by the Scrum Team and stays consistent rather than being adjusted to the work.

  4. Question 4 · Self-Managing Teams

    A Scrum Master starts each day by assigning the open Sprint Backlog items to individual Developers so nothing is forgotten. How does this relate to the Scrum Guide 2020?

    • It conflicts with Scrum, because the Developers internally decide who does what, when, and how
    • It fits Scrum, because the Scrum Master is accountable for the team's effectiveness
    • It fits Scrum while the team is still new, and it should stop once the Developers have become more experienced
    • It conflicts with Scrum, because assigning the work belongs to the Product Owner

    Why: The Scrum Team section states that Scrum Teams are self-managing, meaning they internally decide who does what, when, and how. The Scrum Master serves by coaching team members in self-management, and the Product Owner has no authority to assign work either.

  5. Question 5 · Done and Undone

    What happens the moment a Product Backlog item meets the Definition of Done?

    • An Increment is born
    • The item is accepted by the Product Owner
    • The item is released to end users
    • The Sprint Goal is considered achieved

    Why: The Increment section states that the moment a Product Backlog item meets the Definition of Done, an Increment is born. Being Done means the work is usable, which is separate from the decision to release it, and the Sprint Goal is an objective for the whole Sprint rather than a single item.

  6. Question 6 · Product Backlog Management

    How does the Scrum Guide 2020 describe Product Backlog refinement?

    • An ongoing activity of breaking down and further defining items into smaller, more precise ones
    • A timeboxed event held once per Sprint and facilitated by the Scrum Master
    • A preparation step that must be completed before the first Sprint starts
    • A Product Owner activity that the Developers join only when they are asked to contribute details

    Why: The Product Backlog section describes refinement as the act of breaking down and further defining Product Backlog items into smaller, more precise items, as an ongoing activity to add details such as description, order, and size. It is not one of the five events, and the Guide sets no fixed cadence or capacity share for it.

  7. Question 7 · Self-Managing Teams

    A stakeholder walks up to the Scrum Master mid-Sprint: "This request is urgent. Please pull Lisa off her current item and put her on it." What is the best response?

    • Reassign Lisa, because urgency outranks process
    • Tell the stakeholder the Scrum Master decides who works on what, and handle it
    • Explain that the Developers decide who does what and when, and connect the stakeholder with the Product Owner to discuss Product Backlog ordering
    • Add the request to the Sprint Backlog so it cannot get lost

    Why: The Scrum Team is self-managing: nobody, including the Scrum Master, tells the Developers how to turn Product Backlog items into Increments. New work is a Product Backlog conversation owned by the Product Owner, who orders it transparently. Reassigning Lisa or claiming the decision hands the Scrum Master people-directing authority that never exists. Adding the request to the Sprint Backlog fails twice: the Sprint Backlog is a plan by and for the Developers, and mid-Sprint scope changes go through the Product Owner, never past the Sprint Goal.

  8. Question 8 · Scrum Framework

    True or false: the Scrum Master must attend the Daily Scrum.

    • True
    • False

    Why: The Daily Scrum is a 15-minute event for the Developers of the Scrum Team. The Scrum Master ensures the event takes place and stays within its timebox, but attendance is not required. Product Owner and Scrum Master participate as Developers only when they actively work on items in the Sprint Backlog. The trap is company habit: in many organizations the standup is a status report to the Scrum Master, which is exactly the answer pattern the exam likes to offer.

  9. Question 9 · Scrum Framework

    Which of the following are commitments tied to the Scrum artifacts? (Choose the best three answers.)

    • Product Goal
    • Sprint Goal
    • Definition of Done
    • Sprint Budget
    • Release Plan

    Why: Each artifact carries exactly one commitment: the Product Backlog has the Product Goal, the Sprint Backlog has the Sprint Goal, the Increment has the Definition of Done. Budgets and release plans can be reasonable tools, but they are not Scrum commitments. The exam shuffles these pairs on purpose ("the Sprint Goal is the commitment of the Increment"), so the mapping is free points once memorized cold.

  10. Question 10 · Done and Undone

    The Sprint timebox expires and two Product Backlog items are only partially finished. What happens?

    • The Sprint is extended until the items are done
    • The partial work is added to the Increment anyway
    • The Sprint ends on time, and the unfinished items return to the Product Backlog, where the Product Owner re-orders them
    • The Scrum Master decides whether to extend the Sprint

    Why: A Sprint is fixed in length and never extended. Work is either Done or not: there is no partial credit, and undone items cannot become part of the Increment. They go back to the Product Backlog for re-ordering; they do not automatically roll into the next Sprint. The only early exit from a Sprint is cancellation by the Product Owner when the Sprint Goal becomes obsolete.

  11. Question 11 · Product Backlog Management

    Who is accountable for effective Product Backlog management?

    • The Scrum Master
    • The Product Owner
    • The Developers
    • The stakeholders

    Why: The Product Owner is accountable for maximizing the value of the product, and effective Product Backlog management is how they do it. The nuance the exam tests again and again: the Product Owner may delegate the work, such as writing items or refining them with the Developers, but the accountability stays with them either way. Any option that moves the accountability to the team, a committee or management is wrong.

  12. Question 12 · Scrum Framework

    For a one-month Sprint, what is the maximum timebox of the Sprint Retrospective?

    • One hour
    • Two hours
    • Three hours
    • Four hours

    Why: The Scrum Guide 2020 sets maximums, not prescriptions: Sprint Planning up to 8 hours, Sprint Review up to 4 hours, Sprint Retrospective up to 3 hours, each for a one-month Sprint and usually shorter for shorter Sprints. The Daily Scrum is the exception that never scales: always 15 minutes. Options stating exact durations ("the Review lasts four hours") are wrong in the other direction.

What to expect

Realistic exam-style questions

20 questions in the style and difficulty of the real PSM I exam, spanning the focus areas Scrum.org publishes for it.

Instant results per focus area

Right after submitting you see your score against the 85% pass mark, broken down by focus area, so you know exactly where you stand.

An explanation for every question

Every answer explains why it is right or wrong, based on the Scrum Guide 2020.

What this free PSM I mock test covers

The 20 questions come from the same reviewed pool as our full exam simulations and span the focus areas of the real PSM I exam: the Scrum framework, the people and accountabilities, and working on the product. Every answer — right or wrong — comes with an explanation of why it is right or wrong, based on the Scrum Guide 2020, so a wrong answer teaches you something instead of just counting against you.

The real PSM I exam runs online at Scrum.org: 80 questions in 60 minutes, and you need at least 85% to pass. The attempt costs $200, there is no required course, and the certification is valid for life once you pass. Twenty questions cannot replace that, but they answer the question that matters first: how far from exam-ready you are today.

You do not need an account or an email address. Your answers are saved as you go, and the moment you submit you get your score against the 85% pass mark, a breakdown per focus area, and the full review with every explanation.

What the PSM I exam covers

The official focus areas from Scrum.org: the free sample touches them, the full simulation weights them by our exam-derived distribution.

Understanding and Applying the Scrum Framework

Empiricism, Scrum values, and how accountabilities, events, and artifacts fit together.

Developing People and Teams

Self-management, coaching, facilitation, and helping a Scrum Team grow.

Managing Products with Agility

Product Backlog, forecasting, and delivering value in an agile environment.

PSM I mock test: frequently asked questions

Want the full PSM I picture?

20 questions are a snapshot. The full simulation gives you 80 questions in 60 minutes under real exam conditions, plus weakness analysis and a Pass Guarantee.

The real exam costs $200 per attempt; full PSM I preparation is a one-time $29.